Structural steel frame of the Test and Fill Facility under construction
01 · Energy Island · Early Works

Test & Fill Facility

Design through field construction of a ~167-foot-tall sodium test facility, delivered as an early-works package ahead of full site mobilization.

Overview

Proving sodium systems before the reactor needs them

The Test & Fill Facility is a non-nuclear building on the Natrium site where sodium systems and components are tested and where the sodium coolant is prepared for the plant. Because it sits outside the nuclear island, it could be designed and built before the NRC construction permit was issued, making it one of the first permanent structures on the site.

As architectural lead, I owned the building's architecture from design development through construction documents and into the field: the enclosure, plans, sections, elevations, roof, reflected ceilings, egress and life safety, plus the specifications, scopes of work, and material takeoffs the procurement and construction teams built from.

Construction carried the building through structural steel erection and completion of the exterior enclosure. During that period I responded to RFIs and resolved field conditions, keeping the early-works package moving ahead of the full site mobilization in April 2026.

Building typeSodium test and fill facility (non-nuclear)
FootprintApprox. 125 × 220 ft
HeightApprox. 167 ft
StructureBraced steel frame with metal panel enclosure
DeliveryEarly-works package, ahead of full site mobilization
RoleArchitectural lead, design development through construction administration
StatusExterior enclosure complete
  • Revit
  • AutoCAD
  • Navisworks
  • Specifications
  • RFI response
  • Life safety
Construction

From steel to skin

Kemmerer, WY
Rendering of the Test and Fill Facility with sodium test building, receipt tank, and office trailer labeled
Design rendering of the facility and its sodium receipt tankRendering · TerraPower via ANS
Structural steel of the Test and Fill Facility during erection
Structural steel erection, January 2026 site tourSite photo
Test and Fill Facility with metal panel enclosure being installed by cranes
Enclosure installation with sodium tanks in the foregroundSite photo
Test and Fill Facility with exterior enclosure complete against the Wyoming hills
Exterior enclosure completeSite photo
  • Floor plans, roof plan, reflected ceiling plans, elevations, sections, and details
  • Egress and life safety plans for a tall, open-volume industrial building
  • Specifications, scopes of work, material takeoffs, and service requisitions
  • Coordination with Structural on the braced frame and enclosure attachment
  • Coordination with Plant Design and Mechanical on equipment access and clearances
  • RFI responses and field-condition resolution through enclosure completion
Scope

What the package contained

An industrial test building has few of the finishes of a conventional project and all of the coordination. The architecture has to hold tolerances for large equipment, provide safe egress from elevated platforms, and deliver an enclosure that can be procured and erected on an accelerated early-works schedule.

Next: Reactor Auxiliary Building